Supplier comparison sheet
Cedar Ridge Machine invented example
- Request
- SRC-0142
- Job
- 250 brackets, 17-4 PH
- Customer quote due
- Friday, 4:00 PM
- Sheet returned
- Wednesday, 10:40 AM
- Round 1 8 RFQs to 6 suppliers, Tue 9:12 AM
- Round 2 Email to the 3 still silent, Wed 8:02 AM
- Phone Ridgeline, still silent on both lines, Wed 9:30 AM
Line 1 Passivation, AMS 2700 Method 1, 250 pcs
| Supplier | Price | Lead time | Minimum | Replied |
|---|---|---|---|---|
| Kestrel Metal Finishing | $1.15 / pc $287.50 lot | 4 business days | $250 per lot | Tue 3:41 PM |
| Their words“Price holds 30 days. Add one day if the parts land after 2 PM.” | ||||
| Halverson Passivating | $0.92 / pc $230.00 lot | 6 business days | $300 per lot | Wed 8:15 AM |
| Their words“That lot is under our minimum, so it bills at $300 either way.” | ||||
| Ridgeline Surface Co | No reply | Not quoted | Not quoted | 2 emails, 1 call |
Line 2 Black oxide, MIL-DTL-13924 Class 1, 250 pcs
| Supplier | Price | Lead time | Minimum | Replied |
|---|---|---|---|---|
| Foundry Row Coatings | $0.88 / pc $220.00 lot | 3 business days | None stated | Tue 2:05 PM |
| Their words“Two days is possible for a $95 flat expedite charge.” | ||||
| Halverson Passivating | $0.74 / pc $185.00 lot | 5 business days | $200 per lot | Tue 4:20 PM |
| Their words“We have not racked this part before, so the price may move after the first article.” | ||||
| Ridgeline Surface Co | No reply | Not quoted | Not quoted | 2 emails, 1 call |
Line 3 17-4 PH bar, 1.25 in round, condition A, 40 ft
Bar is bought annealed. Heat treat to H900 is handled elsewhere on this job, after machining and before the finishing lines above.
| Supplier | Price | Lead time | Minimum | Replied |
|---|---|---|---|---|
| Delta Bar & Plate | $18.40 / ft $736.00 total | In stock, ships next day | 20 ft | Tue 11:50 AM |
| Their words“Mill test reports come with it. Price is good for 7 days.” | ||||
| Wolcott Metals | $17.95 / ft $718.00 total | 9 business days | 40 ft | Wed 9:05 AM |
| Their words“This is mill delivery, not stock. I cannot confirm the 9 days until the mill releases it.” | ||||
Five things for you to decide
- Ridgeline Surface Co answered nothing on either line. Emailed Tue 9:12 AM and Wed 8:02 AM, called Wed 9:30 AM, voicemail left.
- The first email to Ridgeline bounced once. The address on your list may be stale.
- Halverson is the cheaper passivation price per piece and the more expensive one per lot at this quantity, because of the $300 minimum.
- Halverson's black oxide lot comes to $185.00 against its own $200 minimum, so that line bills at $200. Still under Foundry Row's $220.
- Wolcott called its own 9 days unconfirmed. That is their sentence, not our estimate.
Read the exact RFQ text your suppliers received
Subject: RFQ · Passivation · 250 pcs 17-4 PH brackets · need a price by Wed 9:00 AM Hi Dana, Cedar Ridge Machine is quoting a job this week and we would like a price from you. Operation: Passivation per AMS 2700, Method 1 Material: 17-4 PH stainless, condition H900 Quantity: 250 pieces, one time Part size: 4.2 x 1.8 x 0.5 in, about 0.4 lb each Drawing: CRM-4471 rev C attached, pages 1 and 2 only Certification: Certificate of conformance with the shipment Parts needed: Back to us by Thursday 24 September Ship to: Cedar Ridge Machine, 1480 Foundry Street, Erie, PA 16510 Please send price per piece and per lot, lead time in business days, your lot minimum, and anything about this part that changes the price. If you cannot quote by Wednesday 9:00 AM, one line telling us so is more useful than silence. Thanks, Ray Okonjo, Cedar Ridge Machine (814) 555-0142 · [email protected]
Invented shop, invented suppliers, invented prices. Nothing on this sheet came from a real quote.